CE5I
22503
1 The determination of actual cost of the work before execution of project is- (A) Costing
- (B) Estimating
- (C) Rate Analysis
- (D) None of above
2 For preliminary discussion of any project
- (A) Approximate estimate
- (B) Detailed estimate
- (C) Revised estimate
- (D) Supplementary estimate
3 While preparing a detailed estimate
- (A) Dimensions should be measured correct to 0.01m.
- (B) Area should be measured correct to 0.01m^Option
- (C) Volume should be measured correct to 0.01m^Option
- (D) All the above
4 The method adopted to have a proper and effective control over the expenses and production cost in an organization is called as
- (A) Administrative Approval
- (B) Technical Sanction
- (C) Costing
- (D) Budget Provision
5 The size of the room is 6m X 3m. The quantity of flooring is
- (A) 18 sq.m
- (B) 18 cu.m
- (C) 18 RMT
- (D) 18 m
6 In long and short wall method of estimation, the length of long wall is the center-to-center distance between the walls and
- (A) half breadth of wall on each side
- (B) Breadth of the wall
- (C) one fourth breadth of wall on each side
- (D) None of the above
7 The modes of measurement of barbed wire fencing is
- (A) RMT
- (B) Cu.m
- (C) Sq.m
- (D) Nos.
8 Which estimate is used when there is change in design and actual cost of construction and also found some additional work?
- (A) Revised Estimate
- (B) Revised and Supplementary Estimate
- (C) Supplementary Estimate
- (D) Renovation Estimate
9 Minimum cover provided for RCC Beam is
- (A) 15mm
- (B) 20mm
- (C) 25mm
- (D) 40mm
10 The mode of measurement of Ornamental Cornice is
- (A) RMT
- (B) sq.m
- (C) cu.m
- (D) Nos.
11 The service unit of prison is
- (A) cell
- (B) student
- (C) classroom
- (D) seat
12 The size of the room is 5m X 4m. The quantity of internal plaster is
- (A) 18cu.m
- (B) 30sq.m
- (C) 18sq.m
- (D) 18RMT
13 The expenses which cannot be seen while preparing estimate but occurs during the execution of work are
- (A) Contingencies
- (B) Work Charged Establishment
- (C) Centage Charges
- (D) Day Work
14 Steps in preparation of detailed estimate are
- (A) Finding out quantities
- (B) Calculation of areas/volume
- (C) Abstracting
- (D) All the above
15 Data required for detailed estimate are
- (A) Drawing
- (B) Rates
- (C) Specification
- (D) All the above
16 Length of one side bent up bar is
- (A) L = (Total length – cover) + 18 x diameter of bar
- (B) L = (Total length – cover) + 18 x diameter of bar + 0.42 x depth of bar
- (C) L = (Total length – cover) + 12 x diameter of bar
- (D) None of the above
17 Steel quantity is expressed in terms of tabular form it is called as
- (A) Estimating
- (B) Bar Bending Schedule
- (C) Costing
- (D) Rate Analysis
18 The size of the room is 4m X 5m. The quantity of ceiling plaster is
- (A) 20cu.m
- (B) 20sq.m
- (C) 20RMT
- (D) 20m
19 The methods for taking out quantities are
- (A) Center line method
- (B) Long wall and Short wall method
- (C) PWD method
- (D) All the above
20 According to ISI method of measurement, the order of the sequence is
- (A) Length, Breadth, Height
- (B) Breadth, Length, Height
- (C) Height, Length, Breadth
- (D) None of these
21 In which method of approximate estimate, structure is divided into two parts i.e., substructure and superstructure?
- (A) Typical Bay Method
- (B) Center Line Method
- (C) Service Unit Method
- (D) Approximate Quantity Method
22 The size of room is 6mx5m Calculate the quantity of skirting below 30cm.
- (A) 22sq.m
- (B) 22cu.m
- (C) 22RMT
- (D) 22m
23 The plinth area of building is equal to 150 sq.m. The approximate cost of that building is Rs. 1,50,000/-. Find plinth area rate of the building by plinth area method.
- (A) Rs.2000/sq.m
- (B) Rs.1500/sq.m
- (C) Rs.1000/sq.m
- (D) Rs.3000/sq.m
24 24. Prepare approximate estimate for school building. 1) No of classroom = 12 2) Rate per classroom = Rs. 12,000
- (A) Rs.2,40,000/-
- (B) Rs.1,20,000/-
- (C) Rs.1,44,000/-
- (D) Rs.3,60,000/-
25 Centage Charges considered as
- (A) 10 – 15 %
- (B) 2 -5 %
- (C) 1 – 2 %
- (D) None of the above
26 The cost of articles or materials at the shop is called as
- (A) Provisional Sum
- (B) Prime Cost
- (C) Day work
- (D) None of the above
27 Purposes of detailed estimate
- (A) To sanction the amount of money required for work.
- (B) For inviting tenders.
- (C) To have a rough idea of the materials required for the work.
- (D) All of the above.
28 The length of item by center line method is
- (A) L = Total c/c length – 1/2 x Number of junction x width of item
- (B) L = Total c/c length – Number of junction x width of item
- (C) L = Total c/c length – 2 x Number of junction x width of item
- (D) None of the above.